TAPS was planned in the late 1960s and early 1970s as a means to transport oil from Alaska's North Slope to Valdez for shipping to other destinations by tanker. TAPS was built between 1974 and 1977 and has been in continuous operation since 1977.
The concept of transporting oil south from Alaska was discussed as early as the 1960s. In 1968, large crude oil reserves were discovered at Prudhoe Bay by the Atlantic Richfield Company (ARCO). ARCO joined with BP Oil and Humble Oil to form the Trans-Alaska Pipeline Systems (TAPS). TAPS was proposed to ship crude oil to the southern Alaska seaport of Valdez (an ice-free port), from where it would be shipped to refineries by tanker.
Pipeline construction from Prudhoe Bay required transiting a route where much of the right-of-way was on federal and state lands. Legislation (the Trans-Alaska Pipeline Authorization Act [P.L. 93-153]) was required to end what had become a stalemate over the route. This right-of-way legislation enabled the pipeline to be constructed.
Environmental studies for the pipeline were started and applications for permits submitted in 1968. Suits were filed by environmental groups and others to block pipeline construction in 1970. Several Native villages filed a lawsuit claiming the pipeline would cross their land. The land ownership question was settled with Congressional passage of the Alaska Native Land Claims Settlement Act and its signature into law by President Richard Nixon in December 1971.
The 48-inch special cold-weather steel was ordered from Japan in April 1969. The building permit for the pipeline was issued in 1974.
Actual construction began in April 1974 and was completed in June 1977 at a cost of approximately $8 billion. At the time, it was the largest privately funded construction project in history. Approximately 2,000 contractors and subcontractors, as well as approximately 70,000 workers, were employed to work on the project.
Paralleling the pipeline from Livengood to Deadhorse, the Dalton Highway (locally known as the Haul Road) was built as a supply route for use in construction, operation, and maintenance of the northern portion of TAPS and the oil fields on the North Slope. This road is now a State highway.
TAPS ConstructionTAPS has been in continuous operation since June 1977.
| Date | Event |
|---|---|
|
March 1968
|
Oil discovered at Prudhoe Bay |
|
August 14, 1970
|
Alyeska Pipeline Service Company incorporated by the owner companies |
|
March, 1972
|
Department of Interior issues final environmental impact statement for TAPS |
|
November 16, 1973
|
Trans-Alaska Pipeline Authorization Act signed into law |
|
January 23, 1974
|
Federal Agreement and Grant of Right-of-Way |
|
May 3, 1974
|
State Lease |
|
April 29, 1974
|
Haul Road construction begins |
|
September 29, 1974
|
Haul Road construction completed |
|
May 27, 1975
|
First pipe laid (Tonsina River) |
|
October 11, 1975
|
Yukon River bridge completed |
|
May 31, 1977
|
Final pipeline weld |
|
June 20, 1977
|
First oil flows from Pump Station 1 |
|
July 28, 1977
|
First oil reached VMT |
|
August 1, 1977
|
First oil-laden tanker (ARCO Juneau) leaves Valdez Marine Terminal |
|
July 1, 1979
|
Drag reducing agent first used |
|
1988
|
Peak average daily throughput of 2.03 million bbl/day |
|
March 24, 1989
|
Exxon Valdez oil spill |
|
July 10, 1989
|
Alyeska Ship Escort/Response Vessel System established |
|
1990
|
Federal Oil Pollution Act of 1990 |
|
1990
|
Joint Pipeline Office established |
|
1990
|
Prince William Sound Regional Citizens Advisory Council contract signed with Alyeska |
|
1990
|
HB 567 enacted by Alaska Legislature amending oil pollution laws |
|
1991
|
Atigun reroute |
|
1993
|
Congressional hearings on TAPS operations |
|
March 5, 1994
|
10 billionth bbl reaches VMT |
|
1996 - 1997
|
Pump Stations 2, 6, 8, and 10 taken off-line and placed on standby due to lower throughput |
|
1997
|
Tanker vapor recovery system added at VMT |
|
August 12, 1997
|
15,000th tanker leaves VMT |
|
April 27, 2000
|
13 billionth barrel reaches VMT |